ESTABLISHMENT OF
CHICKEN LAYERS PROJECT
A
project is a planned set of interrelated tasks to be expected over a fixed and
within a certain cost and other limitations.
Our
project worth 20 million of which 15 million is the loan from Mkombozi Bank and
our own contribution is 5 million. This project is the benefit based with the
five year implementation. Different techniques of project decision criteria
will be used to determine if the project is recommended to be implemented. The
techniques are:
- · Benefit Cost Ratio (BCR)
- · Net Present Value (NPV)
- · Internal Rate of Return (IRR)
The
cost will be incurred by our project will be divided in the following explanations;
Read More: Project Planning and Management (A Case of Kwimba District)
EQUIPMENT COSTS
S/N
|
Equipment
|
Quantity
|
@
Price
|
Total
Cost
|
1
|
Chicken shed (rent)
|
1
|
2,000,000
|
2,000,000.00
|
2
|
Trays
|
100
|
2,000
|
200,000.00
|
3
|
Feeders at
·
Chick level
·
Chicken level
|
300
150
|
2,000
3,000
|
600,000.00
450,000.00
|
4
|
Electricity bulbs
|
50
|
1,000
|
50,000.00
|
5
|
Wheel barrow
|
2
|
50,000
|
100,000.00
|
6
|
Spade
|
2
|
15,000
|
30,000.00
|
7
|
Blooms
|
5
|
2,000
|
10,000.00
|
8
|
Exercise books
|
2
|
3,000
|
6,000.00
|
9
|
Pens
|
5
|
200
|
1,000.00
|
10
|
Weight
|
1
|
200,000
|
200,000.00
|
11
|
Generator
|
1
|
800,000
|
800,000.00
|
Grand total
|
4,447,000/=
|
MATERIAL COST
S/N
|
Material
|
Quantity
|
@
Cost (price)
|
Total
cost (price)
|
|
1
|
Food
|
25,833 Kgs
|
275.00
|
6,625,000.00
|
|
2
|
Chicks
|
2,000
|
1,500
|
3,000,000.00
|
|
3
|
Drugs
i.
Antibiotics
ii.
Vaccines
|
60 Kgs
60 Kgs
|
4,000.00
4,000.00
|
240,000.00
240,000.00
|
|
4
|
Glucose
|
40 packets
|
500.00
|
20,000.00
|
|
Grand total
|
10,125,000/=
|
OTHER COSTS INCLUDING LABOUR
S/N
|
Per month
|
Per year
|
Total
|
|
1
|
Four (4) people
|
100,000
|
1,200,000
|
3,600,000
|
2
|
Water
|
50,000
|
600,000
|
600,000
|
3
|
Electricity
|
20,000
|
240,000
|
240,000
|
4
|
Announcement and setting cost
|
5,000
|
||
5
|
Communication costs
|
20,000
|
||
6
|
Miscellaneous
|
963,000/=
|
||
Grand
total
|
5,428,000/=
|
Loan from Mkombozi
bank has to be paid in the 10% interest rate
Provided loan is
15,000,000/=
How the loan is
going to be paid the bellow information explain
The compounding formula
needs to be used in order to find the future value from the present benefits.
Therefore, 15,000,000/=
million after five years
From;
FV = PV (1+i)t
Where,
FV
= Future Value
PV = Present Value
i = interest rate
t = time
Given;
PV= 15,000,000
I =10%
t = 5 years
FV = 15,000,000(1+0.1)5
FV = 15,000,000(1.1 )t
FV = 15,000,000(1.6105)
FV = 24,157,650
Future value is 24,157,650/= Tshs to be paid for 5 years.
Therefore, we are
required to pay Mkombozi bank 4,831,530 each year for five years at the
interest rate of 10%.
BENEFIT OF THE FIRST
YEAR
At
the first year the project will produce for six month; where per day will
produce 300,000/=, T.shs, per month will be 9,000,000/= Tshs and per half of
whole year will produce 54,000,000 which complete the first year (Gross
Benefit).
Costs
RUNNING
COSTS INCURRED DURING THE FIRST YEAR
|
|||
S/N
|
Item
|
Per
month
|
Total
Per year
|
1
|
Food
|
2,250,000/=
|
20,500,000/=
|
2
|
Drugs
|
40,000/=
|
240,000/=
|
3
|
Electricity bill
payment
|
20,000/=
|
120,000/=
|
4
|
Water bill payment
|
15,000/=
|
90,000/=
|
5
|
4 Labors
|
@ 100,000/=
|
2,400,000/=
|
6
|
Loan payment
|
-
|
4,831,530/=
|
7
|
Tax payment
|
-
|
13,500,000/=
|
Grand
total
|
41,681,530/=
|
Therefore,
Net benefit =
Gross Benefit – all costs
Net profit for
first year = 54,000,000 – 41,681,530
=
12,318,470/=
Net profit for
the first year is 12,318,470/=
BENEFIT OF THE SECOND
YEAR
The project will
produce 385,000/= per day for the second year which 11,550,000/= per month and
138,600,000/= per year (Gross Benefit).
Costs
RUNNING
COSTS INCURRED DURING THE SECOND YEAR
|
||||
S/N
|
Item
|
Per
month
|
Total
Per year
|
|
1.
|
Food
|
1,968,750
|
23,625,000/=
|
|
2.
|
Chicks
|
5,000,000/=
|
||
3.
|
Feeders
|
500,000/=
|
||
4.
|
Water bill payment
|
25,000
|
300,000/=
|
|
5.
|
Electricity bill payment
|
23333.30
|
280,000/=
|
|
6.
|
Tax payment
|
17,000,000/=
|
||
7.
|
4 Labors
|
@ 225,000/=
|
10,800,000/=
|
|
8.
|
Buying car
|
20,000,000/=
|
||
9.
|
Loan payment
|
4,831,530/=
|
||
10.
|
Transport cost
|
5,663,470/=
|
||
11.
|
Chicken shed renting
|
8,000,000/=
|
||
Grand
Total
|
96,000,000/=
|
Therefore,
Net benefit=
gross benefit – all costs
Net benefit for
the second year = 108,000,000 - 96,000,000
=
12,000,000/=
Net benefit for
the second year = 12,000,000/= (undiscounted cash flow).
BENEFITS OF THE THIRD
YEAR
The
project will produce 300,000/= per day, 9,000,000/= per month and 99,000,000/=
per year. (gross benefits).
COSTS
Running
costs incurred during the third year
|
|||
S/N
|
Item
|
Per
month
|
Total
per year
|
1.
|
Food
|
2,250,000/=
|
35,000,000/=
|
2.
|
Water bill payment
|
16.666.60
|
200,000/=
|
3.
|
Electricity bill
payment
|
20,833.30
|
250,000/=
|
4.
|
4 labors
|
329,000/=
|
15,800,000/=
|
5.
|
Tax payment
|
2,250,000/=
|
27,000,000/=
|
6.
|
Transport cost
|
15,800,000/=
|
|
7.
|
Loan payment
|
4,831,530/=
|
|
Grand
total
|
93,081,530/=
|
Therefore,
Net benefit =
Gross benefit – All costs
Net benefits for
third year = 108,000,000/= - 93,081,530/=
Net benefit for
third year is 14,918,470/= T.shs
BENEFITS OF THE FOURTH
YEAR
The
project will produce 275,000/= per day for the first year, which is equal to
8,250,000/= per month and 99,000,000/= per year (Gross benefits).
COSTS
Running
Costs incurred during the fourth year
|
|||
S/N
|
Item
|
Costs
per Month
|
Total
Per year
|
1.
|
Water bills payment
|
18,333.30
|
220,000/=
|
2.
|
Electricity bill
payment
|
22,500/=
|
270,000/=
|
3.
|
4 labors
|
@ 225,000/=
|
10,800,000/=
|
4.
|
Food
|
35,000,000/=
|
|
5.
|
Chicks
|
6,000,000/=
|
|
6.
|
Tax payment
|
24,750,000/=
|
|
7.
|
Transport costs
|
5,500,000/=
|
|
8.
|
Loan payment
|
4,831,530/=
|
|
9.
|
Communication costs
|
500,000/=
|
|
Grand
total
|
87,871,530/=
|
Net
benefit = Gross benefit – All costs
Net
benefits for the fourth year = 99,000,000/= - 87,871,530/=
=
11,126,470/=
Net
benefits for the fourth year is 11,126,470/=
BENEFITS FOR THE FIFTH
YEAR
The
project will produce 165,000/= per day for the fifth year which is 4,950,000
per month and 59,400,000/= per year.
COSTS
Running
cost during the fifth year
|
|||
S/N
|
Items
|
Costs
per Month
|
Total
Costs per Year
|
1.
|
Water bill payment
|
18,333.30
|
220,000/=
|
2.
|
Electricity bill
payment
|
25,000/=
|
300.000/=
|
3.
|
4 labor payment
|
@ 300,000/=
|
14,400,000/=
|
4.
|
Food
|
32,000,000/=
|
|
5.
|
Tax payment
|
14,850,000/=
|
|
6.
|
Communication Costs
|
520,000/=
|
|
7.
|
Transport cost
|
8,000,000/=
|
|
8.
|
Loan payment
|
4,831,530/=
|
|
Grand
total
|
67,921,530/=
|
Therefore,
Net
benefit = Gross benefits – All costs
Net
benefit for the fifth year = 59,400,000/= - 67,921,530/=
=
-8,921,570/=
Net
benefits for fifth year = -8,921,570/=
After the analysis of
net benefits of each year, then we need to calculate; the Benefit Cost Ratio
(BCR), the Net Present Value (NPV) and Internal Rate of Return (IRR).
a)
THE
BENEFIT COST RATIO
Benefit
cost ratio (BCR) =
Io= 20,000,000
NPVt=8,212,723.95+5,332,800+4,420,342.66+2,174,970.77+-1,17 4,970.77-20,000,000
NPVt=18,988,768.7-20,000,000
NPVt=-1,174,970.77
Therefore, the net present Value (NPV) is equal to -1,174,970.77 which will be used as NPV2
Therefore,
the benefit cost ratio (BCR) of the chicken layering is 1.7. This project is
worth to undertaken.
a)
NET
PRESENT VALUE (NPV)
To calculate NPV is
given by the formulaNPVt + PV1 + PV2 + PV3… + PVt - Io
Before
we calculate the NPV we have to calculate the discounted cash flow at the rate
of 10%.
This is given by the
formula,
This
has summarized in the table below
NPV
(THE CASH FLOW IN T.SHs
|
|||
Year
|
Cash
Flow in T.shs
|
Discounting
factors at 10%
|
Discounted
Cash Flow
|
0
|
20,000,000/=
|
||
1
|
12,318,400/=
|
0.9091
|
11,198,721.08
|
2
|
12,000,000/=
|
0.8264
|
9,916,800.00
|
3
|
14,918,470/=
|
0.7515
|
11,208,246.51
|
4
|
11,128,470/=
|
0.6830
|
7,600,745.01
|
5
|
-8,921,570/=
|
0.6209
|
-5,539,402.09
|
NPV
|
33,845,707.79
|
From,
Therefore to calculate
the NPVt at the interest rate of 10% is given by:
NPVt + PV1 + PV2 + PV3… + PVt - Io
Given,
Io = 20,000,000
PV1 = 11,198,721.08
PV2 =
9,916,800
PV3 =
11,208,246.51
PV4 = 7,600,745
PV5 = 5,539,402.09
NPVt=11,198,721.08+9,916,800+11,208,246.51+7,600,745+-5,539 ,402.09-20,000,000
NPVt = 33,845,707.79-20,000,000
NPVt = 13,845,707.79
Therefore,
the net present Value (NPV) is equal to 13,845,707.79
a) THE INTERNAL RATE OF RETURN
To calculate the
IRR there is a need of to find the NPV2 with a negative value
because there is already NPV1 with the positive value. The NPV2
here is calculated using at the rate of 50% as follows:
This has
summarized in the table below
Year
|
Cash
Flow in T.shs
|
Discounting
factors at 50%
|
Discounted
Cash Flow
|
0
|
20,000,000/=
|
Df = 1/(1+i)t
|
|
1
|
12,318,400/=
|
0.6667
|
8,212,723.95
|
2
|
12,000,000/=
|
0.4444
|
5,332,800.00
|
3
|
14,918,470/=
|
0.2963
|
4,420,342.66
|
4
|
11,128,470/=
|
0.1975
|
2,197,872.86
|
5
|
-8,921,570/=
|
0.1317
|
-1,174,970.77
|
NPV
|
18,988,768.7
|
From,
Therefore
to calculate the NPVt at the interest rate of 50% is given by:NPVt + PV1 + PV2 + PV3… + PVt - Io
Given,
PV1 =
8,212,723.95
PV2 =
5,332,800.00
PV3 =
4,420,342.66
PV4 =
2,197,872.86
PV5 =
-1,174,970.77
NPVt=8,212,723.95+5,332,800+4,420,342.66+2,174,970.77+-1,17 4,970.77-20,000,000
NPVt=18,988,768.7-20,000,000
NPVt=-1,174,970.77
Therefore, the net present Value (NPV) is equal to -1,174,970.77 which will be used as NPV2
Therefore, IRR (the
Internal Rate of Return) is given by the formula:
Where,
IRR= Internal rate of Return
NPV1 =
Highest NPV (with positive
value)
NPV2 =
Lowest NPV (with negative
value)
R1 = Discount rate for NPV1
R2
= Discount rate for
NPV2
Given data,
IRR= …?
NPV1 =
13,845,707.79
NPV2 =
-1,011,231.3
R1 = 0.1
R2
= 0.5
Therefore,
IRR= 0.5
IRR= 50%
Therefore, the Internal Rate of
Return is 50%.
All
in all this project (chicken rearing establishment), is worth because it has
the Net Present Value of 33,845,707.79 which is greater than zero. Also this
project will have more benefit than coast Ratio of 1.7; This shows that the
project will have more benefits than costs. The internal rate of return is 50%,
this shows the maximum interest rate that the project could pay for the
resources used if the project is to recover its investment and operating costs
and still break even.
Read More: Project Planning and Management (A Case of Kwimba District)
Hello Every One, I am Robbort Bassler From Ohio U.S.A, I quickly want to use this medium to shear a testimony on how God directed me to a Legit and real loan lender who have transformed my life from grass to grace, from being poor to a rich woman who can now boast of a healthy and wealthy life without stress or financial difficulties. After so many months of trying to get a loan on the Internet and was scammed the sum of $9,800 i became so desperate in getting a loan from a legit loan lender on-line who will not add to my pains, then i decided to contact a friend of mine who recently got a loan on-line, we discussed about the issue and to our conclusion she told me about a woman called Mrs Christina Rojas who is the C.E.O of Happiness Loan Firm So i applied for a loan sum of (750,000.00USD) with low interest rate of 3%, so the loan was approved easily without stress and all the preparations where made concerning the loan transfer and in less than two(2) days the loan was deposited into my bank so i want to advice everyone in need of a loan to quickly contact him via: Email: (Happinessloanfirm2478@hotmail.com) he does not know am doing this i pray that God will bless him for the good thing he has done in my life.
ReplyDelete